Posted on: January 24, 2019

NOTICE TO THE GENERAL PUBLIC OF UPDATED WORK SCHEDULE FOR PAVING, DRAINAGE & UTILITY IMPROVEMENTS

  NOTICE TO THE GENERAL PUBLIC OF UPDATED WORK SCHEDULE  

Construction throughout the Woodland Park project is moving forward and now that we have a better idea of the work output, we can offer an updated work timeline and changes in the remaining work Phases to improve on this.

The contractor has asked to break the work on Lotus and Lotus Court into smaller phases and move this work ahead of Oleander and Yaupon Streets.  The attached phasing plan has been updated to reflect these changes and the new projected timeline.

We will continue to release Public Notices as the contractor moves into new Phases of construction as usual and we will update the construction schedule if needed.

Expect, periodic traffic disruptions and restricted access through the work zone.  Please observe construction zone regulations of the directional and speed limit signs being erected and being enforced by our police department.  Please be considerate of your neighbor’s safety as well as your own as you share the street into and out of work zones.  We appreciate your patience and apologize for any inconveniences these needed improvement changes may create for you.

Sincerely,

Sal Aguirre, P.E.

City Engineer